Bitdeer Acquires 101 MW Gas Power Plant in Alberta for Bitcoin Mining

Bitdeer, a Bitcoin mining company, acquired a 101-MW gas-fired power plant near Fox Creek, Alberta for a vertically integrated BTC mining operation.

  • The site marks Bitdeer's first project in Canada and follows collaboration with government agencies and the Canadian Blockchain Consortium.
  • Bitdeer plans to build a 99 MW datacenter capable of scaling up to 1 GW.
  • Energy production costs are estimated between $20 and $25 per MW/h.
  • The facility has a 99 MW interconnect license to the local power grid, allowing Bitdeer to sell power back during high demand.
  • Site preparation and infrastructure development are set to begin in Q2 2025, with full operations expected by Q4 2026.